Skip to content Skip to footer

Green Energy Project

Up  to now

Structure

Co-development in a JV and/or through a DSA (development service agreement)

Total Capacity 282,9MW PV 

Target
• Development and implementation of 14 PV projects 229,20MW
• Ground-mounted projects in Greek mainland
• Required land: appr 3.570 str
• Connection to existing or new SS
• Capacity (per project) >>1MW
• Clustering based on the common grid connection point
• Trackers and/or bifacial modules wherever applicable
• Private PPA and/or through auction procedures

 

LocationCentral & West GreeceTechnologyPhotovoltaicOutput260MWNo of projects18Commencement date6/2019StatusUnder DevelopmentShare